- Home
- Departments
- Public Works
- Sewer Utility and Collection System
- SE Area Combined Sewer Improvements
- When Will Construction Start?
The MMSD Edgewood Near Surface Collector project construction is currently scheduled to begin in the fall of 2021 and conclude in spring 2023. Visit the project web page for more details.
The first phase of the Village’s Southeast Area Combined Sewer Improvement Program is anticipated to begin in early 2023. In addition to the sewer improvements, work is expected to include watermain relay and lead service line replacement, ash tree replacement, road reconstruction/restoration and possible green infrastructure enhancements. Visit the project construction webpage here.
A second phase is slated for 2024 construction. The project scope is expected to include watermain replacement, ash tree replacement, road reconstruction/restoration and possible green infrastructure enhancements. An illustration of the 2024 Phase II conceptual plan can be viewed here; please note this is subject to change based upon the final engineering design..
The final phase of the sewer improvements is scheduled to coincide with the reconstruction of Lake Drive (STH 32) by the Wisconsin Department of Transportation in 2025. Please view the conceptual plan here; please note this is subject to change based upon the final engineering design.