What's Planned?

MMSD Edgewood NSC

The Milwaukee Metropolitan Sewerage district is currently in the design phase of this project. Construction is anticipated to begin in mid- 2021 and conclude in early 2023 at an estimated cost of $15.7 million. The project will impact the Edgewood corridor from N. Maryland Avenue to the Milwaukee River.

A presentation was made to the Shorewood Village Board on August 3, 2020 which provided an overview of the project, presented the preliminary engineering and design concept, outlined the preliminary alignment and construction approach, identified the project construction impact areas and reviewed the project's public outreach plan.

map schedule

CSSA Downspout Disconnection Program

MMSD Chapter 3 Management, Operations, and Maintenance of Tributary Sewers requires the disconnection of downspouts within the combined sewer service area by January 1, 2025.  The Village is currently developing an implementation plan for this mandatory effort.

MMSD: Partners for a Cleaner Environment
aerial project area

Southeast Area Combined Sewer Improvements (SEASCI)

The proposed project scope includes the installation over of 11,000 lineal feet of sewer pipe, some watermain replacement and restoration or reconstruction of impacted roadway as noted on the conceptual illustration at right. Final engineering analysis may alter pipe sizes or routes. The improvements are anticipated to be constructed in three phases beginning in : 2023. The total estimated cost for all phases is approximately $22 million.


rain barrel pic2