2018 Wilson Drive Reconstruction

North Wilson Drive in the Village of Shorewood is scheduled for a full reconstruction in 2018.  A contract for the work is anticipated to be awarded by the Village Board on March 5, 2018.  A detailed schedule will be developed by the selected contract; the following general timeline is anticipated:

   •     March - April       Utility relocation (gas, electric, phone, data/cable, etc.)
   •     May                     road construction work begins
   •     September          substantial completion (roadway fully opened to traffic; landscape, lighting, other work may remain)
   •     October               final completion

Planning and Design Process

Nearly two years was spent planning for the design of Wilson Drive by a large and dedicated group of volunteers.  Please click here to learn more about this extensive process.